Planned engineering work at Carstairs is set to take place between the evening of Friday 3 March and Tuesday 30 May 2023 which means LNER services will be unable to serve Motherwell and Glasgow Central.
During this twelve-week period, Network Rail Scotland will carry out improvement work at Carstairs Junction.
It’s part of a wider ongoing project which includes re-configuring and renewing the existing track, along with associated signals and overhead lines.
The project – which has already seen the start of track renewals and overhead line installation work – will improve punctuality, infrastructure reliability, and line speeds on routes between Glasgow and Edinburgh via Carstairs.
The following alterations will apply to LNER services from the evening of Friday 3 March until Tuesday 30 May 2023:
Monday to Friday
Saturday
Sunday
Customers travelling to and from Glasgow should use ScotRail services via Queen Street.
Full LNER timetable information can be found at www.lner.co.uk/timetable